Condo renovation approval in Malaysia: management, deposit and council

Before any work starts in a condo, someone has to say yes in writing. This guide covers who approves what, which rules are law and which are your building’s own, and how to apply without losing weeks.

The short answer: ask your management office first, always. For some work you also need the local authority (in Kuala Lumpur, that is Kuala Lumpur City Hall, or DBKL). Most of the rest, such as working hours, passes and the deposit amount, is decided by your building.

Who approves what

WhoWhat they decide
Management: the joint management body (JMB) or management corporation (MC) that runs your buildingWritten approval before any renovation starts. Whether to ask for a deposit and a completion date. Which documents to ask for. House rules on hours, passes, lifts and debris.
Local authority (DBKL in KL, your local council elsewhere)Permits for certain work only, listed below. Finding out whether you need one is the owner’s responsibility.
DeveloperDefects in a new unit, during the defect liability period. Not renovation approval.

Management comes first because it is the gate for everything. The council question sits with you as the owner, so settle it before work starts, not after.

What the standard by-laws say

The standard strata by-laws sit in the Third Schedule of the Strata Management (Maintenance and Management) Regulations 2015. By-laws 27 to 29 deal with renovations. In plain words:

  • Written approval before work. You must not start renovation works without prior written approval from the management, and from the authority where necessary.
  • A deposit and a completion date may be required. The management can ask for a deposit to secure compliance and can require the work to be finished within a set time. The by-laws set no amount.
  • You check the council question. The owner must find out whether council approval is needed, and get it if it is.
  • Structure stays intact. Work must not weaken structural members, including shear walls and load-bearing beams or columns.
  • Wet areas: 150 mm waterproofing upturn. When you change the floor finish in a bathroom or other wet area, the waterproofing membrane is replaced and turned up the walls by at least 150 mm.
  • No hacking or drilling within 300 mm of concealed pipes or conduits. Ask your contractor how they will find hidden pipes and wiring before they drill.
  • Facade and external windows. Changes to the facade, balcony or external windows need the management’s approval.

Your building may add its own rules on top.

Work that needs both the management and the authority

Some work needs prior written approval from the local authority and the management, together. The by-laws list:

  • building a raised platform or a new floor level
  • relocating an external door or window
  • shifting plumbing or sewerage (moving a toilet, sink or floor waste)
  • changing or upgrading the whole electrical system of the unit
  • removing or changing building safety features

So a full rewire, a moved toilet or a raised platform is not a “management only” job. Permits may also be needed for structural, facade, plumbing-relocation or platform work generally. Never assume “no permit needed”, and never assume every renovation needs the council either. It depends on the work. We check this for clients before the design is fixed.

House rules, not law

The following are set by each building, not by the by-laws:

  • working hours and working days
  • contractor passes and ID
  • lift protection and service-lift booking
  • debris removal arrangements
  • the deposit amount

Your building’s house rules decide. As an example only, a common pattern is weekdays 9am to 5pm, sometimes Saturday mornings, and no Sundays or public holidays. Published examples in the Klang Valley often show a refundable deposit of RM1,000 to RM5,000. Treat both as examples. Your building may be stricter, and the amount can be higher or lower.

How to apply, step by step

Steps marked varies differ from building to building.

  1. Ask the management office for the renovation guidelines and the application form. Ask for the house rules too. Request them by email so you have them in writing.
  2. Gather the documents the building asks for. Varies. The form tells you what is needed. It may include drawings of the changes, your contractor’s details and a work schedule.
  3. Settle the council question before you submit. If any item in the list above needs the authority, getting that approval is your responsibility. Ask the management how they want it shown in your application.
  4. Submit and wait for written approval. Varies. Management approval often takes 1 to 2 weeks, but that is set by the building. Do not let anyone start hacking before the approval is in writing.
  5. Pay the deposit. Varies. The amount, how to pay and any extra fees are set by the building. Keep the receipt.
  6. Register contractors and book the lift. Varies. Your building may require passes for workers and a booking for the service lift for deliveries and debris.
  7. Photograph the common areas before work starts. Lift, corridor, lobby. If the deposit is later questioned, you have a record.
  8. Ask about the final inspection and the refund. Varies. How the deposit is refunded, and how long it takes, is set by the building, so ask when you pay.

Contractors: check the CIDB registration

Construction contractors in Malaysia must be registered with CIDB, the Construction Industry Development Board. See CIDB’s contractor registration page. Ask your contractor for the registration number, and put the contractor’s name on your contract.

If you bought a new unit

A new unit bought from a developer under the standard sale and purchase agreement has a 24-month defect liability period from the date you take vacant possession. This is explained in the housing ministry’s defect liability FAQ (KPKT). Sub-sale purchases are different, so check your agreement.

The practical rule: report defects in writing, with photos, before any renovation work starts. The developer must repair within 30 days of receiving your written notice. The developer is only responsible for defects in its own work, so record them before anything is hacked or tiled over. If a dispute with the developer over defects in a new unit cannot be settled, it goes to the Tribunal for Homebuyer Claims.

Our new condo checklist walks through the order of things from key collection to move-in.

Kuala Lumpur: adding rooms

In KL, DBKL has restricted adding internal walls to create extra bedrooms in strata buildings. Check before planning an extra room, especially if a layout idea relies on splitting a space. In other areas, ask your local council.

Common questions

Do I need DBKL or council approval for my condo renovation?

Not always. Management approval is needed for any renovation. Council approval is also needed for certain work, such as shifting plumbing, relocating external doors or windows, adding a platform, or changing the whole electrical system. Ask before you assume either way.

How much is the renovation deposit?

Each building sets its own. Published examples in the Klang Valley are often RM1,000 to RM5,000, refundable. Ask your management office for the exact amount and how the refund works.

Are working hours set by law?

No. Hours, days, passes and lift protection are your building’s house rules. A common example is weekdays 9am to 5pm, sometimes Saturday mornings, with no Sundays or public holidays.

Can I change my balcony or external windows?

You need the management’s approval for any change to the facade, balcony or external windows. Relocating an external door or window also needs the authority’s approval.

Can I start before the approval comes?

No. The by-laws require prior written approval from the management before renovation work starts.

How we handle this for clients

We handle the management-office application and coordinate the contractors. Layout changes are checked against council and building rules before we design them.

If you have a question about approvals for your own unit, message us on WhatsApp. We usually reply within one business day.

Useful next steps:

These are planning notes, not legal advice. Your building’s by-laws and house rules, and the authority’s own requirements, decide in the end.