Free tool, no sign-up

Condo renovation timeline planner

Tell it what you are renovating and when you want to start. You get a dated plan: the stages in the right order, the approvals that come first, the 2027 festive breaks, and an earliest and a latest handover date. No phone number asked.

Our planning estimates: about 5 to 8 weeks on site for a new unit fit-out and about 9 to 15 weeks for a full renovation, after about 3 to 6 weeks of design, drawings and quotation and often 1 to 2 weeks for management approval.

Your renovation and your dates

1 Your unit and the work
What are you starting with?
How much are you doing?

New kitchen and wardrobes, plaster ceiling in the living areas, extra power and lighting points, air-conditioners and paint. The existing floors and bathrooms are kept.

2 Design and dates
Is the design done?

The start date is when design begins. Add a target date and the planner works backwards from it.

Week by week

Your dated schedule

Every stage has two bars. The solid bar is when it runs if every stage goes quickly. The pale bar is when it runs if every stage takes its time. Carpentry is made off site while the work on site carries on.

Example This plan starts on Tue 1 Dec 2026. Change the start date and it becomes yours.

3 Your building and the calendar

Three assumptions behind these dates. Change any of them and the schedule follows. We submit the application to your management office when you sign off the design.

Management office approval
1 to 2 weeks
Set by your building. Often 1 to 2 weeks. Ask your management office.
Chinese New Year pause
2 weeks
6 and 7 February 2027. Work stops Mon 1 Feb to Sun 14 Feb 2027.
Hari Raya Aidilfitri pause
1 week
10 and 11 March 2027, subject to official confirmation. Work stops Mon 8 Mar to Sun 14 Mar 2027.

Many contractors and suppliers stop work around each festival. How long is up to them, so set what yours tells you. Festive dates beyond March 2027 are not built in.

  • Earliest plan
  • Latest plan
  • Made off site
  • Festive pause
  • Checkpoint
  • +14 daysMoved later by a festive break
  1. Before work startscounting from Tue 1 Dec 2026
  2. Defects reported to the developer
    Tue 1 Dec

    Report defects to the developer in writing, with photos, before any hacking. The developer is only responsible for defects in its own work. Under the standard sale and purchase agreement for a new home, the defect liability period is 24 months from vacant possession and the developer must repair within 30 days of receiving your notice: by 31 Dec if it arrives on 1 Dec. In the earliest plan, work on site starts before then.

  3. Brief, site measure and layout options1 to 2 weeks
    Earliest: 1 to 7 Dec
    Latest: 1 to 14 Dec
  4. Design development, 3D views and itemised quotation2 to 4 weeks
    Earliest: 8 to 21 Dec
    Latest: 15 Dec to 11 Jan
  5. Management office approval1 to 2 weeks
    Earliest: 22 to 28 Dec
    Latest: 12 to 25 Jan
  6. Written approval in hand
    Earliest: Tue 29 Dec
    Latest: Tue 26 Jan

    Written approval from your management office before work starts. Required under the standard strata by-laws. Your building sets how long it takes, and may ask for a deposit and set a completion date.

  7. If any plumbing moves: two approvals

    If the design moves a toilet, sink or floor waste, that needs approval from both the management and the local authority. This plan allows time for the management only. We have no verified figure for how long a local authority takes, so none is added. We check what your unit needs.

  8. On sitefrom Tue 29 Dec at the earliest, Tue 26 Jan at the latest
  9. Plumbing and electrical first fixhalf a week to 1.5 weeks
    Earliest: 29 Dec to 1 Jan
    Latest: 26 Jan to 19 Feb +14 days: work stops for the Chinese New Year break
  10. Carpentry made off site3 to 5 weeks, in parallel
    Earliest: 29 Dec to 18 Jan
    Latest: 26 Jan to 22 Mar +21 days: work stops for the Chinese New Year and Hari Raya Aidilfitri break
  11. Plaster ceilinghalf a week to 1 week
    Earliest: 2 to 5 Jan
    Latest: 20 to 26 Feb +14 days: moved later by a festive break earlier in the plan
  12. Paintinghalf a week to 1 week
    Earliest: 6 to 9 Jan
    Latest: 27 Feb to 5 Mar +14 days: moved later by a festive break earlier in the plan
  13. Carpentry installation1 to 1.5 weeks
    Earliest: 19 to 25 Jan
    Latest: 23 Mar to 2 Apr +21 days: moved later by a festive break earlier in the plan
  14. Second fix: lights, switches, air-conditioners and fittingshalf a week to 1 week
    Earliest: 19 to 22 Jan
    Latest: 23 to 29 Mar +21 days: moved later by a festive break earlier in the plan
  15. Cleaningabout half a week
    Earliest: 26 to 29 Jan
    Latest: 3 to 6 Apr +21 days: moved later by a festive break earlier in the plan
  16. Defects list and handoverhalf a week to 1 week
    Earliest: 30 Jan to 16 Feb +14 days: work stops for the Chinese New Year break
    Latest: 7 to 13 Apr +21 days: moved later by a festive break earlier in the plan
  17. HandoverCleaned, checked and handed to you
    Earliest: Tue 16 Feb
    Latest: Tue 13 Apr
  • Every duration is our planning estimate, shown as a range. None of them is a published standard or a promise. Approvals, deliveries and festive breaks can move the dates.
  • The earliest plan runs every stage at the short end of its range. The latest plan runs every stage at the long end.
  • Stages are counted in calendar days. Weekends and public holidays are not taken out, apart from the two festive pauses. The start of work and handover are shown on weekdays. Your building's house rules decide which days and hours work is allowed.
  • Festive pauses stop site work and carpentry fabrication. Design work and the management office's review are not paused. Dates beyond March 2027 are not built in, and this plan runs past them: allow for later holidays yourself.

Price this scope in the cost calculator

Interior Designer KL · interiordesignerkl.com/renovation-timeline-planner/ · WhatsApp +60 16-756 4007 · Planning estimates, not a promise. Approvals, deliveries and festive breaks can move the dates.

Stage by stage

The order of works, and why

Wet and dusty work first, finished surfaces last. Each stage sits where it does for a reason. A contractor may swap two neighbouring steps with good cause. Ask what the cause is.

  1. 1 to 2 weeks

    Brief, site measure and layout options

    It starts with how you live, what you want to spend and a measured survey of the unit. Layout options follow. The layout is settled first because every pipe, socket and cabinet follows from it, and a change on paper costs nothing to undo.

  2. 2 to 4 weeks

    Design development, 3D views and itemised quotation

    The chosen layout is developed into drawings and 3D views of the main spaces, and materials are selected so they can be ordered in good time. The stage ends with an itemised quotation. Nothing is built until you have agreed it.

  3. 1 to 2 weeks

    Management office approval

    Under the standard strata by-laws, renovation work needs written approval from the management (the JMB or MC) before it starts. We submit the application to your management office when you sign off the design, and work on site can start only once the approval comes through. The management may ask for a deposit and set a completion date.

  4. half a week to 1.5 weeks

    Protection, hacking and strip-out

    Floors, doors and anything being kept are covered first, along with the lift and corridor where your building's house rules ask for it. Then old tiles, fittings and built-ins come out. The noisiest, dustiest work goes first so that nothing new is damaged by it, and no hacking or drilling is allowed within 300 mm of concealed pipes or conduits.

  5. half a week to 1.5 weeks

    Plumbing and electrical first fix

    Pipes, drains, wiring, conduits and air-conditioner piping are run while the walls, floors and ceilings are still open. This fixes the position of every socket, switch, light and water point, which is why the design has to be settled before work starts.

  6. 1.5 to 3 weeks

    Waterproofing and tiling

    Wet areas are waterproofed and tiled, and any new floor tiles are laid. Changing the floor finish in a bathroom or other wet area means replacing the waterproofing membrane, turned up the walls by at least 150 mm. Wet work finishes before ceilings, paint and carpentry because water and cement dust would spoil them.

  7. 3 to 5 weeks, off site

    Carpentry made off site

    Final measurements are taken once the wet works are done, because a fitted cabinet has to match the finished walls and floors, not the bare ones. The kitchen, wardrobes and other built-ins are then made in a workshop while the ceiling and painting carry on. It is the longest single wait in the plan, and the site can look quiet while it happens.

  8. half a week to 1 week

    Plaster ceiling

    The ceiling frame and boards go up once the wiring and air-conditioner piping above them are in place. Positions for downlights and cove lighting are cut here, so the lighting plan has to be final.

  9. half a week to 1 week

    Painting

    Walls and ceilings are painted while the rooms are still empty, which is quicker and cleaner than painting around cabinets. Painters return for touch-ups once the carpentry and fittings are in.

  10. 1 to 1.5 weeks

    Carpentry installation

    Cabinets, wardrobes and countertops are delivered and fitted. Deliveries usually need a lift booking, and your building's house rules decide the hours.

  11. half a week to 1 week

    Second fix: lights, switches, air-conditioners and fittings

    Lights, switches, sockets, air-conditioners, taps and sanitary fittings are fitted and connected. This runs alongside the carpentry installation, because the sink, hob and cabinet lighting can only be connected once the cabinets are in place.

  12. about half a week

    SPC or vinyl flooring

    SPC or vinyl planks go down late, after the painting and once the cabinets and fittings are in, so that ladders, paint and tools do not mark the new floor. Some contractors lay it before the cabinets and cover it instead. Either order works if the floor is protected.

  13. about half a week

    Cleaning

    A post-renovation clean takes fine dust off every surface, inside the cabinets included. It comes before the final check because dust hides defects.

  14. half a week to 1 week

    Defects list and handover

    We walk through the unit with you and write a defects list. The contractors put the items right, and handover happens when the list has been checked off with you.

Our planning estimates

How long each stage takes

We found no verified, published durations for renovation stages in Malaysia, so we do not quote any. These ranges are our own planning estimates. The planner uses exactly these numbers, and a real programme is set once we have seen your unit and your building's rules.

Our planning estimate for each renovation stage, in weeks, with when the stage applies
Stage, and when it appliesOur planning estimate
Brief, site measure and layout optionsWhen the design is still to be done 1 to 2 weeks
Design development, 3D views and itemised quotationWhen the design is still to be done 2 to 4 weeks
Management office approvalEvery renovation. Your building sets the time, so change it in the planner 1 to 2 weeks
Protection, hacking and strip-outOnly with bathrooms, retiling or the strip-out of old built-ins in a sub-sale unit half a week to 1.5 weeksAdd half a week to 1 week when the floors are hacked as well as the bathrooms
Plumbing and electrical first fixEvery plan half a week to 1.5 weeksAdd about half a week when the whole unit is rewired, making it 1 to 2 weeks
Waterproofing and tilingOnly with bathrooms or retiling 1.5 to 3 weeksAdd 1 to 1.5 weeks when the floors are retiled as well as the bathrooms
Carpentry made off siteWith a new kitchen and wardrobes. Runs in parallel with the site work 3 to 5 weeks
Plaster ceilingWith a plaster ceiling half a week to 1 week
PaintingEvery plan half a week to 1 week
Carpentry installationWith a new kitchen and wardrobes 1 to 1.5 weeks
Second fix: lights, switches, air-conditioners and fittingsEvery plan. Alongside the carpentry installation where there is one half a week to 1 week
SPC or vinyl flooringWith SPC or vinyl laid over the existing floor about half a week
CleaningEvery plan about half a week
Defects list and handoverEvery plan half a week to 1 week

Last reviewed 25 November 2026. A week is seven calendar days.

What that adds up to

Design, drawings and quotation
about 3 to 6 weeks
Management approval
often 1 to 2 weeks
On site, new unit fit-out
about 5 to 8 weeks
On site, full renovation
about 9 to 15 weeks

The on-site totals are worked out by the planner from the table, so the two always agree. They are shorter than the sum of the rows because carpentry is made while other stages run.

These are planning estimates, not a promise. Approvals, deliveries and festive breaks can move the dates.

Why plans slip

What moves the dates

Approvals

Work cannot start until your management office has approved it in writing, and your building sets how long that takes. Some work, such as moving plumbing or rewiring the whole unit, also needs the local authority's approval. The planner flags that work, but does not put a duration on it.

Material and carpentry lead times

Carpentry is measured after the wet works, so it cannot be made early. Tiles, countertops, sanitary ware and air-conditioners each have their own delivery time. Choosing them during design, not during the work, keeps the site from waiting.

Festive breaks

Chinese New Year falls on 6 and 7 February 2027 and Hari Raya Aidilfitri on 10 and 11 March 2027, subject to official confirmation. Many contractors and suppliers stop for a week or more around each. The planner pauses site work around both, and you can change the length. Dates beyond March 2027 are not built in.

Changes after work starts

A change made on site can mean re-measuring, re-ordering or redoing finished work. Any change is priced and approved by you in writing first. Expect the dates to move with it.

Building working hours

Working hours, working days, lift bookings and debris removal are set by your building's house rules. A common pattern, as an example only, is weekdays 9am to 5pm, sometimes Saturday mornings, and no Sundays or public holidays. Shorter hours make every stage longer.

And what it costs

The cost calculator prices the same scope, item by item, from published Malaysian prices. It opens on the scope you chose here.

Estimate the cost

Questions

Renovation timelines, answered plainly

How long does a condo renovation take in Malaysia?

Our planning estimate is about 5 to 8 weeks on site to fit out a new unit, and about 9 to 15 weeks for a full renovation with bathrooms and flooring. Before that, allow about 3 to 6 weeks for design, drawings and quotation, and often 1 to 2 weeks for your management office to approve the work, which is set by your building. We submit the application to your management office when you sign off the design, so design and approval together take about 4 to 8 weeks and work never starts on the day of sign-off. Approvals, deliveries and festive breaks can move the dates. These are our own planning estimates, not published standards and not a promise.

What is the correct order of renovation work?

Wet and dusty work first, finished surfaces last. Protection and hacking come first, then plumbing and electrical first fix, waterproofing and tiling, the plaster ceiling and painting. Carpentry is measured after the wet works and made off site while that goes on, then installed alongside the second fix of lights, switches and fittings. Flooring laid over the existing floor, cleaning, a defects list and handover close the job. The reason for each step is in the order of works on this page.

Can renovation work be done on weekends?

Your building's house rules decide, not the law. Working days and hours are set by each building. A common pattern, as an example only, is weekdays from 9am to 5pm, sometimes Saturday mornings, and no work on Sundays or public holidays. Ask your management office for its renovation guidelines before you fix any dates.

How long does management approval take?

It is set by your building. Often 1 to 2 weeks, which is what this planner assumes until you change it. We submit the application to your management office when you sign off the design, and the wait runs from that day. Written approval from the management (the JMB or MC) is required before renovation work starts, under the standard strata by-laws, and the management may require a deposit and set a completion date. When we manage a renovation, we handle the management-office application.

What should I do first after collecting my keys?

Report defects to the developer in writing, with photos, before any renovation work starts. A new home bought from a developer under the standard sale and purchase agreement has a 24-month defect liability period from the date of vacant possession, and the developer must repair within 30 days of receiving your notice. Then ask your management office for its renovation guidelines and start on the layout. The keys-to-move-in checklist lists every step.

When should I confirm carpentry?

In this plan, carpentry is measured once the wet works are done, made off site in 3 to 5 weeks and installed in 1 to 1.5 weeks. So the day you confirm it sets the earliest day it can go in. Enter a target move-in date in the planner and it works backwards to the latest date you can confirm. Those durations are our planning estimates.

Does renovating affect my defect liability period?

The developer is only responsible for defects in its own work, so record them before anything is hacked. Report defects in writing, with photos, before any renovation work starts. For a new home bought from a developer under the standard sale and purchase agreement, the defect liability period is 24 months from the date of vacant possession, and the developer must repair within 30 days of receiving your notice. Sub-sale purchases are different: check your agreement.

Can I move in before everything is finished?

It is your decision, but plan for it. This planner assumes you move in after handover, once the unit has been cleaned and a defects list has been checked off with you. The dusty and wet work sits at the front of the order for a reason, and anything left unfinished has to be done around your furniture, during the hours your building's house rules allow. If your date is fixed, enter it as a target in the planner. It shows whether the scope fits and what would have to give.

Keys-to-move-in checklist Condo renovation guide Condo design and managed renovation

A plan is a start. Real dates need your floor plan.

Send us this plan and your floor plan on WhatsApp. We will tell you what is realistic for your unit and your building, and what we would do first. We usually reply within one business day.

Example handover16 Feb to 13 Apr
WhatsApp us